Demo week is done! I think we got through it in good shape. We had only a few unwelcome discoveries. It looks like at one point in time the sink leaked and caused some water damage and mold. We decided to move the kitchen sink and remove the drywall behind it, just to play it safe. There is a silver lining though; To access the space better, Kasey took down the overhead cabinets and it turns out we really liked how it opened up the kitchen space. We decided we are going to tile the entire wall and do floating shelves in place of the over sink cabinets. The sink was also built out 4 inches to allow for cabinet space, so we will gain 4 inches of room back!
But wait! We’re not done yet! We had some more bad news in the bathroom. The 2x4s behind the tile in the shower were completely dry rotted at the base. We will have to replace them all. Luckily for us, they aren’t load bearing, they were just there to support the tile. Kasey redid some sketch wiring and had to take out a bathroom fan just blowing into the floor rafters.
While the demo discoveries definitely added to the list, to be honest, its exactly what we expected. You really just don’t know when you’re popping the lid off of things and you have to be flexible.
Continue reading “Euclid Airbnb Week 2: Demo Days”